Total Budget$291,390$28,610contingency
x
Search your workspace content.
| Line | Basis | ScheduleAugSepOctNovDecJanFebMar | Actions | |||||||
|---|---|---|---|---|---|---|---|---|---|---|
| Discovery3 | Aug 10 to Sep 4, done | $21,350 | $20,910 | 98% | $20,910 | +$440$440 under budget | ||||
| Design3 | Sep 7 to Nov 13, forecast to Nov 16, on track | $39,600 | $36,000 | 91% | $39,300 | +$300$300 under budget | ||||
| 120 h × $150 | Sep 7 to Oct 2, done | $18,000 | $16,800 | $16,800 | −8 h+$1,200$1,200 under budget, 8 fewer hours than planned | |||||
| 96 h × $150 | Sep 21 to Nov 13, forecast to Nov 16, over budget | $14,400 | $12,000 | +6 h−$900$900 over budget, 6 more hours than planned | ||||||
| $7,200 fixed | Oct 12 to Oct 23, done | $7,200 | $7,200 | $7,200 | $0on budget | |||||
| Build5 | Oct 5 to Mar 31, on track | $124,900 | $29,890 | 24% | $119,300 | +$5,600$5,600 under budget | ||||
| 420 h × $165 | Oct 5 to Jan 29, on track | $69,300 | $20,460 | −20 h+$3,300$3,300 under budget, 20 fewer hours than planned | ||||||
| 160 h × $185 | Oct 26 to Jan 22, on track | $29,600 | $5,180 | $0on budget | ||||||
| 6 mo × $2,300 | Oct 5 to Mar 31, on track | $13,800 | $2,300 | −1 mo+$2,300$2,300 under budget, 1 mo fewer than planned | ||||||
| 6 mo × $450 + $1,500 | Oct 8 to Mar 31, spending ahead of time | $4,200 | $1,950 | $0on budget | ||||||
| $8,000 fixed | Jan 18 to Feb 5, not started | $8,000 | $0 | n/aNot started | $0on budget | |||||
| Integrations3 | Oct 12 to Jan 22, on track | $41,800 | $11,400 | 27% | $41,800 | $0on budget | ||||
| $24,000 fixed | Oct 12 to Jan 22, on track | $24,000 | $7,200 | $0on budget | ||||||
| 80 h × $140 | Oct 26 to Dec 25, spending ahead of time | $11,200 | $4,200 | $0on budget | ||||||
| 40 h × $165 | Nov 23 to Dec 11, not started | $6,600 | $0 | n/aNot started | $0on budget | |||||
| Data Migration4 | Oct 19 to Feb 12, over budget | $34,660 | $12,600 | 36% | $40,160 | −$5,500$5,500 over budget | ||||
| 120 h × $150 | Oct 19 to Dec 18, forecast to Jan 3, over budget | $18,000 | $10,500 | +32 h−$4,800$4,800 over budget, 32 more hours than planned | ||||||
| 38 h × $70 | Oct 19 to Nov 27, forecast to Dec 7, over budget | $2,660 | $2,100 | +10 h−$700$700 over budget, 10 more hours than planned | ||||||
| 64 h × $150 | Dec 14 to Feb 5, not started | $9,600 | $0 | n/aNot started | $0on budget | |||||
| 40 h × $110 | Jan 11 to Feb 12, not started | $4,400 | $0 | n/aNot started | $0on budget | |||||
| Launch4 | Jan 25 to Mar 31, not started | $29,080 | $0 | n/aNot started | $29,080 | $0on budget | ||||
| Total | $291,390 | $110,800 | 38% | $290,550 | +$840$840 under budget |